China-Kyrgyzstan-Uzbekistan Railway Gains Pace: First Tunnel Through on Kyrgyz Section
English Summary:
On Sept 5, the China-Kyrgyzstan-Uzbekistan Railway Co. reported the breakthrough of the Koshtor-Bei North No. 2 tunnel — the first tunnel completed on the Kyrgyz section — 209.6 m long, single-track, with a maximum overburden of 41 m. Stage progress is also reported on control works such as the Naryn No. 1 tunnel.
English Summary:
Since full-scale civil works began in June 2025, construction has started on 27 tunnels (one through), 43 bridges and 88 subgrade sections, with foundations underway at 20 stations; all temporary roads and power-supply projects are in service. The line exceeds 500 km in total, with the Kyrgyz section at 304.84 km.
English Summary:
Running from Kashgar via the Torugart pass into Kyrgyzstan, through Jalal-Abad to Andijan in Uzbekistan, the railway is a flagship Belt and Road project of the three countries. Once completed, it will become a new rail corridor linking China and Central Asia. Progress is subject to official releases by the railway company and project parties.